CAPITAL REQUEST Controlling Board No.
DNR0101925
Status:  Approved
Meeting Date:  6/15/2020

GENERAL INFORMATION

Agency
Natural Resources


Division/Institution
Engineering

Eligible for Local Administration?
Yes
Real Estate Acquisition
    Release of Capital Funds(R.C.Sec. 127.14G) and/or R.C.126.14
    Transfer of Capital Funds (R.C.Sec. 127.14G and/or Sec. 127.15)
    Higher Education Authorization Request (Sec. 3333.071)
    Other Statutory Authority/Bill Section:
Fiscal Year(s)
2020
Bill No.
HB 529
Eligible for OBM
Director Approval?
No
Capital Request
    Release of Capital Funds (R.C.Sec. 127.14G)
    Transfer of Capital Funds (R.C.Sec. 127.14G and/or Sec. 127.15)
    Waiver of Competitive Selection (R.C.Sec. 127.16B)
      No Competitive Opportunity
      Agency Released Competitive Opportunity
    Agency Released Competitive Opportunity (R.C.Sec. 127.162)
    Release Percent for Arts (R.C.Sec. 3379.10)
    Other Statutory Authority/Bill Section:
    Other:Change of Intent

VENDOR INFORMATION
For FYAmountNameAddressCounty
DNR01 2020 $475,000.00 Beaver Excavating 2000 BEAVER PLACE AVE SW
Canton, OH 44706
Stark
DNR01 2020 $965,275.00 TAM Construction, Inc. 6648 Hudnell Road
Athens, OH 45701
Athens

TRANSFER INFORMATION
FromToFYFund GroupFund CodeAppropriation Line ItemAppropriation Line Item NameTransfer AmountPrev Rel Amount
         

FUNDING INFORMATION
Fund GroupFund CodeAppropriation Line ItemAppropriation Line Item NameTotal Amount
CPF 7035 C725R3 State Parks Renovations/Upgrades $1,976,112.00
CPF 7035 C725N6 Wastewater/Water Systems Upgrades $2,436,291.86
CPF 7031 C725N5 Wastewater / Water Systems Upgrades $526,285.00
CPF 7035 C725A0 State Parks, Campgrounds, Lodges, Cabins $561,569.00
CPF 7026 C725N7 District Office Renovations $510,275.00

SIGNATURES
     
Mary Mertz 06/15/2020
   
Agency Director or Authorized Agent On The Date Of
   
06/05/2020 W. Fletch Zimpher
   
Date Controlling Board President/OBM Director
   
AGENCY CONTACT
Name:  Danielle Vandegriff Title:  Legislative Director
Phone:  (614) 265 - 6878 Fax:  (614) 261 - 9601 E-Mail:  Danielle.Vandegriff@dnr.state.oh.us
REQUIRED EXPLANATION OF REQUEST
  The Department of Natural Resources respectfully requests Controlling Board approval to release capital funds in the amount of $1,976,112 from Fund 7035, ALI C725R3 (State Parks Renovations/Upgrades), $526,285.00 from Fund 7031, ALI C725N5 (Wastewater/Water System Upgrades), $2,436,291.86 from fund 7035, ALI C725N6 (Wastewater/Water Systems Upgrades), $561,569.00 from fund 7035, ALI C725A0 (State Park, Campgrounds, Lodges, Cabins), and $510,275.00 from fund 7026, ALI C725N7 (District Office Renovations) in FY20, which includes an agency released competitive opportunity to contract with TAM Construction, Inc., Athens, OH, for $965,275 and Beaver Excavating Co., Canton, OH, for $475,000 to provide investigative, design, and construction administration services for improvements at Hocking State Forest and Mosquito State Park, in Hocking and Trumbull counties. Additionally, we request a change of intent in the amount of $475,000 from CB #DNR0101804 to apply unused contingencies to the preconstruction and construction services at Mosquito State Park located in Cortland, OH in Trumbull County.  
  The release of these funds will provide funding for the following contracts: Great Lake Demolition, TAM Construction Inc., MWCD, Jim Santini Builder, Inc., Anderzack-Pitzen Construction, Inc., The Menji Group, LLC, and Unger Construction Ltd for construction improvements at Harrison, Van Buren, Paint Creek, Strouds Run, Jackson Lake, Middle Bass Island, Mohican, Beaver Creek, Hueston Woods, Cowan, and Pike Lake State Parks located across Ohio in Hancock, Fulton, Highland, Athens, Ottawa, Ashland, Richland, Columbiana, Muskingum, Clinton, Pike and Jackson Counties.

See attached Narrative for project description and additional information.
 
  DNR0101577, Approved 11/19/2018
DNR0101676, Approved 4/22/2019
DNR0101693, Approved 5/20/2019
DNR0101711, Approved 6/10/2019
DNR0101715, Approved 06/10/2019
DNR0101804, Approved 12/16/09
 
Attachments Controlling Board Request No.: DNR0101925
Attachment TypeAttachment Description
Other Mosquito Lake Park Map
Bid tabulations/price quotations Bid Tab - Statewide Vault Latrines
Other Project Locations - Statewide Vault Latrines
Bid tabulations/price quotations Bid Tab - Middle Bass Island Vault Latrine
Other Project Location - Middle Bass Island Vault Latrines
Other Agreement - Mohican Sanitary Collection System
Bid tabulations/price quotations Bid Tab - Beaver Creek State Park Horseman?s Campground Well
Other Site Map - Beaver Creek SP Horseman's Campground Well
Other RFQ - Hocking SF Storage Building and Water System
Other Agreement - Hocking SF Storage Building and Water System
Bid tabulations/price quotations Bid Tab - Blue Rock & Hueston Woods Flush Latrine
Other Site Location _ Blue Rock Flush Latrine
Other Site Location - Hueston Woods Flush Latrine
Bid tabulations/price quotations Bid Tab - Cowan Lake WW Collection System
Other Site Location - Cowan Lake WW Collection System
Bid tabulations/price quotations Bid Tab - Pike Lake WW System
Other Site Location - Pike Lake WW System
Other Recommendation Letter - Pike Lake WW System
Other Narratives
 
Release and Permit Information
NameFYAmountR & P #R & P DateIssued ByComments
Beaver Excavating 2020 $475,000.00
TAM Construction, Inc. 2020 $965,275.00

Capital Request Required Information
Architect, Engineering, or Other Professional Service Contracts/Construction Manager at Risk or Design Build Contracts - Beaver Excavating
Controlling Board Request No.: DNR0101925
1. 
Type of Service to be provided: Construction Manager at Risk.
 
2. Selection Process:
a. Explain how the Request for Proposal (RFP)/Request for Qualifications (RFQ) was publicized or advertised.
A Request for Qualifications was published on the OFCC Opportunities web page at http://ofcc.ohio.gov/Opportunities.aspx on December 14, 2018. Two representatives each of OFCC and the Owner reviewed each of the RFQ responses and developed a short list of the most qualified firms, as shown on the attached list. An RFP was then distributed to the shortlisted firms on February 2, 2019.
   
b.
Number of proposals distributed. NA
c.
Number of days in which interested parties had to respond to the RFP/RFQ. 32
d.
Number of proposals received. 3
e. For each proposal or statement of qualifications received, provide name, complete address of the principal place of business, and amount of each proposal (or attached as a list)..
Name Proposal AmountAddressCityStateCounty
2K General $.00 19 Gerber St. Building B Delaware OH Delaware
The Beaver Excavating Company $.00 2000 Beaver Place Avenue S.W. Canton OH Stark
TAM Construction, Inc. $.00 6648 Hudnell Rd Athens OH Athens
   
f. Indicate who rated the responses and was involved in the selection of the contractor.
Each of the proposals from the short-listed firms were evaluated by representatives of OFCC and the Owner. An interview was held to allow evaluators to ask questions about the proposal.
   
3.
Identify the selected contractor. Beaver Excavating
 
  Explain why this contractor was selected.
   
  The firm of The Beaver Excavating Company was selected based on a combination of their experience and knowledge of the project and their pricing proposal in accordance with the ORC Section 9.334, Section 153:1-6-01 of the Ohio Administrative Code, and the standard operating procedures of the Ohio Facilities Construction Commission.
4. Provide contractor's location of their principal place of business. 
 
2000 BEAVER PLACE AVE SW
Canton, OH 44706
County: Stark
5. Provide contractor's location from which all or most or contract work will be performed, if different from the location of principal place of business.
 

 OH 
County:
   
6. Identify all state contracts which the selected contractor has had approved by the Controlling Board since the beginning of the last fiscal year through this fiscal year to date. Also include contracts approved for this agency or institution of higher education.
   
 
a. Total number of contracts: 4
b. For each contract, list the state agency and the contract amount.
AgencyContract/Agreement AmountFY
Natural Resources $22,847,000.00 19
Natural Resources $9,921,903.87 19
Natural Resources $4,819,229.40 19
Natural Resources $7,184,636.66 19
7. 
Provide the following employee information: Nationwide Ohio
Total Number of Employees 405    324   
Percentage of Women 48% 38%
Percentage of Minorities 43% 39%
8.
What percent of the work will be done by subcontractors? 0%
   
If more than 50%, provide the following employee information.
SubcontractorNationwide
# of Employees
Nationwide
% of Women
Nationwide
% of Minorities
Ohio
# of Employees
Ohio
% of Women
Ohio
% of Minorities
9. Fee Analysis: For design-build and construction management at risk services, also provide a fee analysis that includes the following:
 
a. Total estimated construction cost:   $10,148,904.00
 
b. Provide the following information regarding the contractor's fees for the services to be performed. 
 
Fee Analysis Contract Amount Percent of Total Construction Cost
Professional Design Services and/or Construction Management Services/Design-Build   $1,178,908.55   11%
Personnel Cost   $0.00   0%
Testing & Special Inspections   $0.00   0%
General Conditions   $0.00   0%
Design Services Fees(A/E of Record in Design-Build Contract only)   $0.00   0%
Other-CMR Contingency
  $198,438.08   2%
  Refer to the requirements of Revised Code Sections 153.65-153.70.

Capital Request Required Information
Architect, Engineering, or Other Professional Service Contracts/Construction Manager at Risk or Design Build Contracts - TAM Construction, Inc.
Controlling Board Request No.: DNR0101925
1. 
Type of Service to be provided: Design/Build Services.
 
2. Selection Process:
a. Explain how the Request for Proposal (RFP)/Request for Qualifications (RFQ) was publicized or advertised.
A Request for Qualifications (RFQ) was published on the OFCC Opportunities web page at http://ofcc.ohio.gov/Opportunities.aspx on March 09, 2020, as Ohio Register #319, and notifications were emailed to every person registered to receive notifications of qualifications-based selection opportunities.
   
b.
Number of proposals distributed. NA
c.
Number of days in which interested parties had to respond to the RFP/RFQ. 14
d.
Number of proposals received. 3
e. For each proposal or statement of qualifications received, provide name, complete address of the principal place of business, and amount of each proposal (or attached as a list)..
Name Proposal AmountAddressCityStateCounty
Foremost MGMT, Inc. $.00 702 E Main St Jackson OH Jackson
Robertson Construction Services $.00 1801 Thornwood Drive Heath OH Licking
TAM Construction, Inc. $.00 6648 Hudnell Road Athens OH Athens
   
f. Indicate who rated the responses and was involved in the selection of the contractor.
Two Division of Engineering staff and one Owner staff reviewed and scored each statement of qualifications and identified a short list of the most qualified firms, as shown on the attached list. Each of the short-listed firms was interviewed and ranked by representatives of Division of Engineering and the Owner.
   
3.
Identify the selected contractor. TAM Construction, Inc.
 
  Explain why this contractor was selected.
   
  Through the interview and selection process, TAM Construction, Inc. was selected based on the firm's best value score, offered value-added options, and quality of team to perform.
4. Provide contractor's location of their principal place of business. 
 
6648 Hudnell Road
Athens, OH 45701
County: Athens
5. Provide contractor's location from which all or most or contract work will be performed, if different from the location of principal place of business.
 

 OH 
County:
   
6. Identify all state contracts which the selected contractor has had approved by the Controlling Board since the beginning of the last fiscal year through this fiscal year to date. Also include contracts approved for this agency or institution of higher education.
   
 
a. Total number of contracts: 3
b. For each contract, list the state agency and the contract amount.
AgencyContract/Agreement AmountFY
Natural Resources $184,450.00 19
Natural Resources $203,000.00 19
Natural Resources $39,000.00 19
7. 
Provide the following employee information: Nationwide Ohio
Total Number of Employees 25    25   
Percentage of Women 4% 4%
Percentage of Minorities 12% 12%
8.
What percent of the work will be done by subcontractors? 0%
   
If more than 50%, provide the following employee information.
SubcontractorNationwide
# of Employees
Nationwide
% of Women
Nationwide
% of Minorities
Ohio
# of Employees
Ohio
% of Women
Ohio
% of Minorities
9. Fee Analysis: For design-build and construction management at risk services, also provide a fee analysis that includes the following:
 
a. Total estimated construction cost:   $702,859.10
 
b. Provide the following information regarding the contractor's fees for the services to be performed. 
 
Fee Analysis Contract Amount Percent of Total Construction Cost
Professional Design Services and/or Construction Management Services/Design-Build   $152,473.56   21.69%
Personnel Cost   $49,650.89   7.06%
Testing & Special Inspections   $9,100.00   1.29%
General Conditions   $0.00   0%
Design Services Fees(A/E of Record in Design-Build Contract only)   $0.00   0%
Other-Reimbursable
  $9,000.00   1.28%
  Refer to the requirements of Revised Code Sections 153.65-153.70.