State of Ohio - Controlling Board Request
STATE OF OHIO
CONTROLLING BOARD
30 East Broad Street, 34th Floor
Columbus, Ohio 43215-3457
(614) 466-5721 FAX:(614) 466-3813
OPERATING REQUEST Controlling Board No.
DNR0101927
Status:  Approved
Meeting Date:  6/15/2020

GENERAL INFORMATION
Agency
Natural Resources


Division/Institution
Engineering
Waiver of Competitive Selection  (Revised Code Section 127.16B)
      No Competitive Opportunity
      Agency Released Competitive Opportunity
Agency Released Competitive Opportunity (Revised Code Section 127.162)
Other Statutory Authority/Bill Section:
Operating Transfer Request  (Revised Code Section 127.14)
      Appropriation
      Cash
      Other Statutory Authority/Bill Section:
Fiscal Year(s)
2020-2021
Bill No.
HB 166
Eligible for OBM
Director Approval?
No

VENDOR INFORMATION
For FYAmountNameAddressCityStateCountyZip Code
DNR01 2020 $1,500,000.00 TAM Construction, Inc. 6648 Hudnell Road Athens OH Athens 457001
DNR01 2020 $226,625.00 Feinknopf Macioce Schappa Architects 995 West Third Ave. Columbus OH Franklin 43212
DNR01 2021 $.00 TAM Construction, Inc. 6648 Hudnell Road Athens OH Athens 457001
DNR01 2021 $.00 Feinknopf Macioce Schappa Architects 995 West Third Ave. Columbus OH Franklin 43212

FUNDING INFORMATION
Fund GroupFund CodeAppropriation Line ItemAppropriation Line Item NameFYAmountFYAmount
DPF 5120 725605 State Park Operations 2020 $1,726,625.00 2021 $.00

SIGNATURES
     
Mary Mertz 06/15/2020
   
Agency Director or Authorized Agent On The Date Of
   
06/04/2020 W. Fletch Zimpher
   
Date Controlling Board President/OBM Director
   
AGENCY CONTACT
Name:  Danielle Vandegriff Title:  Legislative Director
Phone:  (614) 265 - 6878 Fax:  (614) 261 - 9601 E-Mail:  Danielle.Vandegriff@dnr.state.oh.us
REQUIRED EXPLANATION OF REQUEST
  The Department of Natural Resources respectfully requests Controlling Board approval for an agency released competitive opportunity in the amount of $1,500,000.00, to contract with TAM Construction, Inc., Athens, OH, for Design Build Services for the development of Phase 1 Shawnee Campground in Scioto County, and in the amount of $226,625.00 to contract with Feinknopf Macioce Schappa Architects, Columbus, OH, for Criteria Architect Services for the development of Phase II Shawnee Campground in Scioto County, from Fund 5120, ALI 725605 (State Park Operations).  
  Shawnee Campground is located in the Appalachian foothills near the banks of the Ohio River, 1,095-acre Shawnee State Park is nestled in the 63,000-acre Shawnee State Forest. Once the hunting grounds of the Shawnee Indians, the region is one of the most picturesque in the state, featuring erosion-carved valleys and wooded hills. The rugged beauty of the area has earned it the nickname "The Little Smokies."

Design/Build services for Phase 1 of the Shawnee new campground will include professional survey, design, permitting, tree removal, grading, road work, excavation, electrical, and plumbing work. Ohio Department of Natural Resources, Division of Parks and Watercraft is developing a modern campground area in the location of the former Shawnee State Park Golf Course to promote recreation. Full-service campsites will include individual utility hookups including electrical, water, and sanitary connections.

A Request for Qualifications was posted in Ohio Register #318 on 02/19/20. Six (6) firms submitted Statements of Qualifications on 03/13/2020. Three (3) were shortlisted to submit proposals in response to the Request for Proposal. TAM Construction, Inc. was selected through a best value-based selection process.

In addition, an Owner Contingency of $113,947.00 is include the amount requested.

TAM Construction, Inc. has proposed a 5% EDGE participation through Self Performed Work, Cardinal Precision Surveying and Resource International.
Phase 2 of the Shawnee new campground project will continue with the roadway, utility infrastructure, and full-service campsite pads to accommodate a total of approximately 100 sites. Utility development will include a new package wastewater treatment facility and necessary pumping stations. Other site improvements will include new restroom/showers within the proposed campground, new campground check-in office, renovations to the existing pro shop converting to retail, and a variety of other possible improvements depending on available project budget including a swimming pool, splash park, amphitheater/event pavilion, archery range, mini golf, bike paths, and fishing piers.

The purpose of this contract is to provide criteria documents for the Design/Build contract for construction of Phase 2 of the Shawnee Campgrounds, including infrastructure, full-service RV hookups, wastewater collection and treatment and roadway. Ohio Department of Natural Resources, Division of Parks and Watercraft is developing a modern campground area in the location of a former golf course to promote recreation. Full-service campsites include individual utility hookups including electrical, water, and sanitary connections.

The development of a complete Program of Requirements (POR) will be included as part of the C-A/E service as an Additional Service. This POR development will include review and validation of the campground planning to define/refine the anticipated programmatic scope. The POR effort should also accomplish a project scope that is prioritized to align with the project budget. Evaluation of the project construction schedule will also be a part of the POR stage.

Request for Qualifications were posted in Ohio Facilities Construction Commission (OFCC) website, formerly the Ohio Register, on March 30, 2020. Eleven (11) firms submitted Statement of Qualifications on April 14, 2020. Three (3) were shortlisted to submit proposals in response to the Request for Proposal. Through the interview and selection process, Feinknopf Macioce Schappa Architects was selected based on the firm's best value score, offered value-added options, and quality of team to perform.

Feinknopf Macioce Schappa Architects has proposed a 10.9% EDGE participation through Metro CD Engineering, LLC (4.77%) and Resource International, Inc. (6.16%).
 
   
Attachments Controlling Board Request No.: DNR0101927
Attachment TypeAttachment Description
Request for Quote (RFQ) RFQ - Shawnee New Campground Phase 1
Contract Agreement - Shawnee New Campground Phase 1
Other Scoresheets - Shawnee New Campground Phase 1
Other Site Map
Request for Quote (RFQ) RFQ - Shawnee New Campground Phase 2
Other Tally Sheet - Shawnee New Campground Phase 2
Contract CAE Agreement
Contract Recommendation letter
 
Release and Permit Information
NameFYAmountR & P #R & P DateIssued ByComments
TAM Construction, Inc. 2020 $1,500,000.00
Feinknopf Macioce Schappa Architects 2020 $226,625.00
TAM Construction, Inc. 2021 $0.00
Feinknopf Macioce Schappa Architects 2021 $0.00

Operating Request Required Information
New Contract - TAM Construction, Inc.
Controlling Board Request No.: DNR0101927
1. Selection Process: Was this contract subject to selection by a Request for Proposal (RFP),
Request for Qualification (RFQ), Request for Information (RFI) process? Yes
 a. Explain how the RFP, RFQ or RFI was publicized or advertised.
     A Request for Qualifications (RFQ) was published on the OFCC Opportunities web page at http://ofcc.ohio.gov/Opportunities.aspx on February 19, 2020, and notifications were emailed to every person registered to receive notifications of best value-based selection opportunities.
 
 b. Number of proposals distributed.  NA
 c. Number of days in which interested parties had to respond to the RFP, RFQ or RFI. 23
 d. Number of proposals received. 3
 e. Information for each proposal received (or see attachment).
Name Proposal AmountAddressCityStateCounty
2K General Company, Inc. $.00 19 Gruber Street Delaware OH Delaware
WAI Construction Group, LLC $.00 1571 Shyville Road Piketon OH Pike
TAM Construction, Inc $.00 6648 Hudnell Road Athens OH Athens
 
 f. Explain why this contractor was selected.
    The firm was selected based on its qualifications, experience, and project knowledge in compliance with the selection process required by R.C. Section 153.69, Administrative Code Section 153:1-1-01, and the standard procedures of OFCC.
 g. Indicate who rated the responses and was involved in the selection of the contractor.
     Each of the short-listed firms was interviewed and ranked by four (4) Department of Natural Resource staff.
 
2. Provide the following selected contractor information:
TAM Construction, Inc.
6648 Hudnell Road
Athens,   OH  457001
County: Athens
 
3. Contractor's location from which all or most of the contract work will be performed, if different from the
location of principal place of business. (For institutional agencies, cite the location of the institution,
including the city and county, where services are to be performed.)


   
4. Institutional agencies only: Is the contractor currently performing services at the institution listed above?
5. Specify the deliverables of this contract or describe the scope of service(s) to be performed by this contractor.
Design Build Services.
6. Cite the account category of expense being used for this purchase of service(s).
Account CategorySubobjectAmountNon-Exempt Amount
570061 $1,500,000.00 $1,500,000.00

 
Total Amounts $1,500,000.00 $1,500,000.00
7.
Duration of this contract (beginning and ending dates) within the fiscal biennium.
Beginning Date Ending Date
06/20/2020 06/30/2021
8. Is the contractor already performing work under this contract? No
   
9. Identify all state contracts which the selected contractor has had approved by the Controlling Board
since the beginning of the last fiscal year through this fiscal year to date. Also include contracts approved
for this agency or institutions of higher education.
a. Total number of contracts. 2
b. For each contract list the state agency and the contract amount.
AgencyContract/Agreement AmountFY
Natural Resources $95,865.11 19
Natural Resources $55,000.00 20
10. Contractor Procurement Compliance:
a. Is this contractor in compliance with Buy America? Yes
  Explain: The materials provided will be per ORC requirements.
   
b. Is this contractor in compliance with Buy Ohio? Yes
Explain: They are on Ohio-based company.
11.
Provide the following employee information: Nationwide Ohio
Total Number of Employees 25    25   
Percentage of Women 4% 4%
Percentage of Minorities 12% 12%
12. What percent of the work will be done by subcontractors?  0
  If more than 50%, provide the same information for each subcontractor as requested in number 11 above for the contractor.
SubcontractorNationwide
# of Employees
Nationwide
% of Women
Nationwide
% of Minorities
Ohio
# of Employees
Ohio
% of Women
Ohio
% of Minorities
13.  Provide all subsequent renewal schedules (beginning and ending dates) and amounts associated with this contract.

A contract renewal is the exercise of an option to enter into a subsequent contract with a vendor in accordance with renewal provisions specified in a preceding contract.
Beginning DateEnding DateTotal Lease Amount
Explain contract provisions. 

Operating Request Required Information
New Contract - Feinknopf Macioce Schappa Architects
Controlling Board Request No.: DNR0101927
1. Selection Process: Was this contract subject to selection by a Request for Proposal (RFP),
Request for Qualification (RFQ), Request for Information (RFI) process? Yes
 a. Explain how the RFP, RFQ or RFI was publicized or advertised.
     A Request for Qualifications (RFQ) was published on the OFCC Opportunities web page at http://ofcc.ohio.gov/Opportunities.aspx on March 30, 2020, and notifications were emailed to every person registered to receive notifications of qualifications-based selection opportunities.
 
 b. Number of proposals distributed.  NA
 c. Number of days in which interested parties had to respond to the RFP, RFQ or RFI. 15
 d. Number of proposals received. 3
 e. Information for each proposal received (or see attachment).
Name Proposal AmountAddressCityStateCounty
STAR Consultants, Inc. $.00 1910 Crown Park Ct. Columbus OH Franklin
Feinknopf Macioce Schappa Architects, Inc. $.00 995 W. Third Ave Columbus OH Franklin
ms consultants, inc. $.00 2221 Schrock Road Columbus OH Franklin
 
 f. Explain why this contractor was selected.
    The firm was selected based on its qualifications, experience, and project knowledge in compliance with the selection process required by R.C. Section 153.69, Administrative Code Section 153:1-1-01, and the standard procedures of OFCC.
 g. Indicate who rated the responses and was involved in the selection of the contractor.
     Two OFCC staff and two Owner staff reviewed and scored each statement of qualifications and identified a short list of the most qualified firms, as shown on the attached list. Each of the short-listed firms was interviewed and ranked by representatives of OFCC and the Owner.
 
2. Provide the following selected contractor information:
Feinknopf Macioce Schappa Architects
995 West Third Ave.
Columbus,   OH  43212
County: Franklin
 
3. Contractor's location from which all or most of the contract work will be performed, if different from the
location of principal place of business. (For institutional agencies, cite the location of the institution,
including the city and county, where services are to be performed.)


   
4. Institutional agencies only: Is the contractor currently performing services at the institution listed above?
5. Specify the deliverables of this contract or describe the scope of service(s) to be performed by this contractor.
Professional Design Services.
6. Cite the account category of expense being used for this purchase of service(s).
Account CategorySubobjectAmountNon-Exempt Amount
570052 $226,625.00 $226,625.00

 
Total Amounts $226,625.00 $226,625.00
7.
Duration of this contract (beginning and ending dates) within the fiscal biennium.
Beginning Date Ending Date
06/20/2020 06/30/2021
8. Is the contractor already performing work under this contract? No
   
9. Identify all state contracts which the selected contractor has had approved by the Controlling Board
since the beginning of the last fiscal year through this fiscal year to date. Also include contracts approved
for this agency or institutions of higher education.
a. Total number of contracts. 2
b. For each contract list the state agency and the contract amount.
AgencyContract/Agreement AmountFY
Natural Resources $95,865.11 19
Natural Resources $55,000.00 20
10. Contractor Procurement Compliance:
a. Is this contractor in compliance with Buy America? Yes
  Explain: The materials provided will be per ORC requirements.
   
b. Is this contractor in compliance with Buy Ohio? Yes
Explain: They are an Ohio-based company.
11.
Provide the following employee information: Nationwide Ohio
Total Number of Employees 28    28   
Percentage of Women 35% 35%
Percentage of Minorities 8% 8%
12. What percent of the work will be done by subcontractors?  45
  If more than 50%, provide the same information for each subcontractor as requested in number 11 above for the contractor.
SubcontractorNationwide
# of Employees
Nationwide
% of Women
Nationwide
% of Minorities
Ohio
# of Employees
Ohio
% of Women
Ohio
% of Minorities
13.  Provide all subsequent renewal schedules (beginning and ending dates) and amounts associated with this contract.

A contract renewal is the exercise of an option to enter into a subsequent contract with a vendor in accordance with renewal provisions specified in a preceding contract.
Beginning DateEnding DateTotal Lease Amount
Explain contract provisions.